North Augusta High School

  • North Augusta High Front

    In November of 2015, we celebrated the completion of Phase 2A of construction and dedicated a 124,095-square-foot facility full of natural light and classrooms, a Freshman Academy, Media Center, Dining Room and Guidance Area.

    In June of 2016, we celebrated the completion of Phase One of North Augusta High's new Math & Business Wing, a beautiful 45,610-square-foot, two-story facility, with a terrazzo floor entrance, seven business labs downstairs and three groups of paired science classrooms with labs and prep rooms on the second floor.

    Phase 2B, which includes a brand new, two-story classroom wing for math, English, foreign language and social studies classes, was completed in October, 2019, clearing the way for the beginning of site prep and construction of Phase 3, which includes a new stadium-style basketball gymnasium.


June 2020 North Augusta High Drone Video





May 2020 Phase 3 Executive Summary Report

If you are having trouble viewing the document, you may download the document.


April 2020 Phase 3 Executive Summary Report

If you are having trouble viewing the document, you may download the document.


March 2020 Phase 3 Executive Summary Report

If you are having trouble viewing the document, you may download the document.


February 2020 Phase 3 Executive Summary Report

If you are having trouble viewing the document, you may download the document.


January 2020 Phase 3 Executive Summary Report

If you are having trouble viewing the document, you may download the document.


Phase 3 Construction Schematic Design Presentation

If you are having trouble viewing the document, you may download the document.






2019-20 Construction Reports

Architect & Contractor Information

  • Architect: McMillan, Pazdan, Smith

    Contractor: H.G. Reynolds

    Delivery Method: Construction Management At Risk


    Design Phases and Decisions with School Stakeholders’ Involvement

    School Board and Office of School Facilities Approval of Each Phase 

    Continual Building began in 2016.


    Schematic Design







CURRENTLY UNDER CONSTRUCTION PHASE 3

  • Design:

    Spring 2018

    Construction and Substantial Completion:

    August 2019 – November 2020

    Total Estimated Project Cost:

    $21 Million

COMPLETED Phase 2B

  • Design:

    January 2015 – December 2015

    Construction and Substantial Completion:

    July 2017 – November 2018

    Total Estimated Project Cost:

    $24.9 Million

COMPLETED Phase 2A

  • Design:

    January 2015 – December 2015

    Construction:

    March 2016 – July 2017

    Total Estimated Project Cost:

    $28.9 Million