North Augusta High School
-
In November of 2015, we celebrated the completion of Phase 2A of construction and dedicated a 124,095-square-foot facility full of natural light and classrooms, a Freshman Academy, Media Center, Dining Room and Guidance Area.
In June of 2016, we celebrated the completion of Phase One of North Augusta High's new Math & Business Wing, a beautiful 45,610-square-foot, two-story facility, with a terrazzo floor entrance, seven business labs downstairs and three groups of paired science classrooms with labs and prep rooms on the second floor.
Phase 2B, which includes a brand new, two-story classroom wing for math, English, foreign language and social studies classes, was completed in October, 2019, clearing the way for the beginning of site prep and construction of Phase 3, which includes a new stadium-style basketball gymnasium.
June 2020 North Augusta High Drone Video
May 2020 Phase 3 Executive Summary Report
April 2020 Phase 3 Executive Summary Report
March 2020 Phase 3 Executive Summary Report
February 2020 Phase 3 Executive Summary Report
January 2020 Phase 3 Executive Summary Report
Phase 3 Construction Schematic Design Presentation
Construction Photo Gallery
2019-20 Construction Reports
2018 Construction Reports
-
Construction Report December 11, 2018
Construction Report November 30, 2018
Construction Report November 28, 2018
Construction Report November 23, 2018
Construction Report November 19, 2018
Construction Report November 16, 2018
Construction Report November 1, 2018
Construction Report October 30, 2018
Construction Report October 25, 2018
Construction Report October 22, 2018
Construction Report October 19, 2018
Construction Report October 1, 2018
Construction Report September 27, 2018
Construction Report July 17, 2018
Construction Report July 12, 2018
Construction Report July 2, 2018
Construction Report June 28, 2018
Construction Report May 17, 2018
Construction Report May 15, 2018
Construction Report May 11, 2018
Construction Report May 3, 2018
Construction Report May 1, 2018
Construction Report April 26, 2018
Construction Report April 24, 2018
Construction Report April 20, 2018
Construction Report April 16, 2018
Construction Report April 12, 2018
Construction Report April 9, 2018
Construction Report April 6, 2018
Construction Report April 3, 2018
Construction Report March 29, 2018
Construction Report March 26, 2018
Construction Report March 22, 2018
Construction Report March 20, 2018
Construction Report March 15, 2018
Construction Report March 13, 2018
2017 Construction Reports
-
Construction Report January 3, 2017
Construction Report January 9, 2017
Construction Report March 14, 2017
Construction Report March 16, 2017
Construction Report March 28, 2017
Construction Report April 4, 2017
Construction Report May 9, 2017
Construction Report May 15, 2017
Construction Report May 18, 2017
Construction Report May 24, 2017
2016 Construction Reports
-
Construction Report May 31, 2016
Construction Report June 6, 2016
Construction Report July 12, 2016
Construction Report July 20, 2016
Construction Report August 9, 2016
Construction Report August 12, 2016
Construction Report August 16, 2016
Construction Report August 18, 2016
Construction Report September 9, 2016
Construction Report September 20, 2016
Construction Report September 27, 2016
Construction Report October 24, 2016
Construction Report November 3, 2016
Construction Report November 8, 2016
Construction Report November 15, 2016
Construction Report November 18, 2016
Construction Report November 22, 2016
Construction Report November 29, 2016
Construction Report December 1, 2016
Construction Report December 5, 2016
Construction Report December 16, 2016
Construction Report December 27, 2016
Construction Report December 29, 2016
STORM WATER COMPLIANCE REPORTS
Architect & Contractor Information
-
Architect: McMillan, Pazdan, Smith
Contractor: H.G. Reynolds
Delivery Method: Construction Management At Risk
Design Phases and Decisions with School Stakeholders’ Involvement
School Board and Office of School Facilities Approval of Each Phase
Continual Building began in 2016.
CURRENTLY UNDER CONSTRUCTION PHASE 3
-
Design:
Spring 2018
Construction and Substantial Completion:
August 2019 – November 2020
Total Estimated Project Cost:
$21 Million
COMPLETED Phase 2B
-
Design:
January 2015 – December 2015
Construction and Substantial Completion:
July 2017 – November 2018
Total Estimated Project Cost:
$24.9 Million
COMPLETED Phase 2A
-
Design:
January 2015 – December 2015
Construction:
March 2016 – July 2017
Total Estimated Project Cost:
$28.9 Million